Daily work rates
Hindi audio
Try it
A job takes 8 days. What share is finished in 2 days?
Show answer
One-quarter of the job, because 2 × 1/8 = 1/4.
Related exam questions
R can do a work in 90 days. What percent work of the total work can be done by R in 45 days?
Aman can do a work in 28 days. What part of the total work can be done by Aman in 8 days?
Amar is 10 percent more efficient than Sachin. If Sachin alone can finish a work in 44 days, then in how many days can Amar finish the same work
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is